Building a brighter future for Miramichi

Aerial views show the ongoing work to date on the Miramichi Wellness Multiplex. 

The construction of the Miramichi Wellness Multiplex is underway of Douglastown Boulevard. The facility will offer an 1860 seat arena, walking track, double gymnasium, 25m/6 lane competition pool, leisure pool as well as enhanced community spaces - all of which incorporate sustainable design features.

This exciting project, expected to open in the fall of 2026, is now progressing through procurement and early construction stages. Stay tuned as we continue to share updates on this development that is sure to benefit the community and create a vibrant hub for all to enjoy.

Ongoing activities

  • Procurement of various sub contractors and supply contracts

  • - more than 30 sub contractors and suppliers are anticipated

  • Site clearing, grading and preparation is complete

  • Building foundations and arena cast concrete walls

  • Pre-cast concrete bleachers under construction

  • Competition pool floor is poured and walls being formed

  • Underground plumbing and electrical services underway

  • Structural steel fabrication underway

  • Upgrading and installation of utility power supply

Upcoming activities

  • Installation of water and sanitary services anticipated to

  • commence in mid September

  • Competition and leisure pool basin construction

  • Pre-cast concrete bleachers installation in October

  • Structural steel installation beginning in October

Please remember this is an active construction site - for your safety and that of our workers, public access is prohibited.

Previous
Previous

Update on Newcastle Water System Upgrades project – September 2024

Next
Next

City Council Highlights for August 13th