Current Project List
FOR THE 2025 YEAR
John Street Reconstruction
Scope includes a full reconstruction of underground services from Church Street to Pyne Street including water, storm, sanitary, road surface and restoration work. The cost is $1,200,000.
2025 Street Resurfacing Program
NORTH
1. Aitken Avenue - McWilliam Street to cul-de-sac - Asphalt Milling & Pave - $ 130,000
2. Bannon Road - Pulverize & Pave - $ 200,000
3. Creaghan Avenue - Excavate & Pave - $ 155,000
4. Crocker Crescent - Overlay - $ 30,000
5. Durick Street - McGrath Cres. to Route B - Asphalt Milling & Pave - $ 55,000
6. Farrer Crescent - Overlay - $ 65,000
7. River Street & Piper Court - Pulverize & Pave - $ 95,000
8. Tardy Avenue - Asphalt Milling & Pave - $ 165,000
SOUTH
1. Barrieau Street - Andrew St. to Raymond St. - Pulverize & Pave - $ 145,000
2. Bremner Drive - Cedar St. to LeBreton Dr. - Pulverize & Pave - $ 150,000
3. Johnson Avenue - Hotel Dieu St. to Church St. - Overlay - $65,000
4. Wallace Road - Civic 30 to Civic 68 - Pulverize & Pave - $200,000
5. Water Street - St. Andrews St. to Civic 2762 - Asphalt Milling & Pave - $ 240,000
6. Water Street - Tozer Ave. to Civic 2706 - Pulverize & Pave - $305,000
The estimated total for the work above is $2,000,000
The City of Miramichi has 225 kilometers of roadway, not including the provincial designated highways. The Department of Engineering reviews and rates each street biannually utilizing software called Total Pave to analyze road conditions.
The selection process for asphalt paving incorporates several considerations which include but are not limited to:
Centennial Bridge Closure, the expected bridge closure is a key contributor to Engineering's recommendations.
PCI - pavement condition index
street designation
traffic volume
street condition
underground infrastructure condition
maintenance costs
street cross section and profile
PSAB 3150 and 3160 (asset management) compliance
Other (development considerations, planning, funding opportunities)